The Cedars-Sinai Marina Towers Breast Imaging project presented multiple challenges during its development. The initial demolition phase revealed unforeseen obstructions above the intended ceiling level, including catwalks, electrical conduits, and water mains.
These elements impeded achieving the desired ceiling heights and required strategic demolition, relocation, or adjustment. Additionally, the team faced a significant challenge with an uneven concrete slab in the reception area, which did not meet ADA compliance standards. This required extensive grinding and slab replacement, a process that was completed within a tight two-week timeframe to ensure the project remained on schedule.
The project involved integrating dual providers within a single space, necessitating meticulous coordination to ensure seamless patient care. The location’s existing infrastructure further complicated the design, requiring constant on-site coordination and adjustments.
For instance, unexpected column placements near the entrance had to be skillfully integrated into the design, affecting ceiling drops and lighting plans. Despite these challenges, the team worked collaboratively to resolve issues swiftly, maintaining both design integrity and project momentum.
Project Challenges:
To address the challenges encountered during the Cedars-Sinai Marina Towers Breast Imaging project, the design and construction teams employed a variety of innovative solutions. The ceiling height obstructions were meticulously mapped and resolved through a combination of targeted demolition, relocation, and adjustment of existing infrastructure. This proactive approach ensured that the design vision could be fully realized without compromising on functionality or aesthetics.
The issue of the uneven concrete slab in the reception area was particularly complex, as it required compliance with ADA standards while maintaining the design's integrity. The team opted to replace the existing slab rather than risk structural instability. This involved weekend and night shifts to complete the work within two weeks, ensuring no delays in the overall project schedule.
Collaboration was key to overcoming these challenges. The teams maintained a continuous dialogue, allowing for quick decision-making and problem-solving on-site. For example, when an unexpected column near the entrance disrupted the planned layout, the design team made rapid adjustments that not only resolved the issue but also enhanced the overall aesthetic, making it appear intentional.
The project’s successful completion ahead of schedule and within budget is a testament to the team’s ability to navigate unforeseen obstacles while maintaining a high standard of design and construction quality.