Project Title – Auditorium Complex at Maritime Academy of Nigeria, Oron
Architect/ Author – Umo, Uduak Peter Ph.D. / U-Peters Associates
Client – Maritime Academy of Nigeria, Oron
Project Date – 2009
Project Era: Contemporary Design
Project Type: Institutional Building
Project Location – The project is located at the communal zone opposite the refectory and beside the library Resource Centre Complex. The topography slopes gradually from the refectory direction to the main entrance road extension. The auditorium is located along this gentle slope. The field that the auditorium is located is surrounded by roads on all the sides. This gives easy access and exit form the site of any anticipated large car traffic.
The main entrance dual carriage road links all other internal roads in the Academy to external Oron town College road that connects other distributor outlet roads in Oron town. The gentle slope of the site and the site being surrounded by gutters offers an opportunity for easy drainage of storm water.
Brief for the project from the management, Maritime Academy included the followings: Auditorium not less than 1500 in capacity.
· Main entrance, Entrance hall,
· Main Multipurpose hall
· Stage
· Provision of exits
· 4 Nos. offices
All above to be on the ground floor.
· Main suspended gallery, exhibition space, offices, conveniences, conference room
· 6 Nos. offices with conveniences
All above to be on the first floor.
Detailed Analysis of the Brief
Site was at the field in front of the Maritime Academy Refectory. Interview with the Rector of Maritime Academy justified their need for the Auditorium as all assembling – reception, worship, meetings with students used to be in the refectory. During the interview with the management staff, they expressed their desire to have an imposing Auditorium. The author established and identified a major symbol - the Maritime Academy logo. The logo that is sculpted in a well landscaped lawn close to the side of the refectory and adjacent to the intended site for the location of the auditorium complex.
All environmental variables, site conditions, soil types and all design parameters, including climatic conditions – acid rain, wind speed as the site is close to river. These considerations and many others influenced the design decisions of the architect.
Outline Proposal: The Architect resolved so many sketch design lines that developed from the use of Maritime Academy logo as design concept. With ideas from various studies and comparative design analysis, a design proposal in the form of sketch plan was obtained at the preliminary stage that satisfied the architectural design parameters and considerations; which included among others functionality, circulation, lighting, ventilation, structural members positioning without blocking vision in the auditorium hall, thermal comfort, acoustics control, vision lines resolutions and other considerations for other allied consultants to perfect.
Services:
Electricity: The professional Engineers, apart from producing drawings that satisfied the auditorium complex lighting, ventilation, security and other requirements; they had the task of making provision for standby electricity options. Power from the academy lines was connected to the Auditorium complex from a step-down transformer in the premises. In addition, a standby generator located at the rear of the complex to provide electricity during periods of power outage was made.
Lighting, Ventilation, Air Conditioning, Security
· Lighting: Apart from designed artificial lighting, the author designed for natural daylighting by providing for glazed windows and fixed lights spanning between columns on the ground and upper floors.
· Ventilation, Air Conditioning: The complex was properly oriented to receive natural all seasonal prevailing winds apart from designed artificial powerful air-conditioning devices.
· Security lines as designed by the author were to be obscured. The engineers utilized the provisions. If the Academy maintains it well, it will be difficult for any criminal to easily identify the lines and gadgets installed in the building complex.
· Water Supply and Drainage: water supply to the building is from the Academy’s supply line but provision was made for a separate water source (borehole) with overhead tanks to service the two edifices in the Academy.
Storm water was drained through to academy sewer. The gentle slope of the site and peripheral drain lines (gutters) simplified the drainage design.
Two septic tanks and soak away pits were provided for the entire complex close to where conveniences are in the building.