Leuven Bioscience Centre

Leuven Bioscience Centre
Marcel IJzerman

Leuven Bioscience Centre

Space for tomorrow’s science
KU Leuven has opened the Leuven Bioscience Centre: a 30,500 m² research and teaching building on the Arenberg III campus in Heverlee. The building was designed by Proof of the Sum in collaboration with SVR-ARCHITECTS, Exilab (part of Sweco), and De Klerck Engineering. Biotechnology serves as the unifying theme between the Department of Biology, several of the university’s research groups, and the microbiology center of the Flemish Institute for Biotechnology (VIB) and KU Leuven. Some 500 researchers, who were previously spread across various locations in the city and on campus, now work together here.
When the design process began in 2018, no one could have predicted what experiments would be taking place in the building nearly a decade later. Research groups grow, merge, and change direction; research techniques continue to evolve; and biosafety regulations are becoming increasingly stringent. That uncertainty became the starting point for the design: a building that adapts to research questions that are not yet known today.

photo_credit Marcel IJzerman
Marcel IJzerman
photo_credit Marcel IJzerman
Marcel IJzerman

A landmark on campus
Arenberg III, part of Arenberg Castle Park, is evolving into a compact campus where dense building blocks alternate with streets and plazas. To accommodate an extensive program on a relatively limited plot, building upward was necessary. The result is a single, clear, slender volume of fourteen stories with a distinctive bend. Together with the IMEC Tower and Arenberg Castle, Leuven Bioscience provides the campus and the broader science cluster with a new landmark.
The bend organizes the building’s layout on the site. It limits the length of the east and west facades and, consequently, exposure to the low-angle sun. Together with the Quadrivium and Leuven Chem&Tech buildings, Leuven Bioscience forms the westernmost campus plaza. The main entrance is situated on a gently sloping landscape, beneath which lies an underground bicycle parking facility for more than 1,500 bicycles that also serves other campus buildings. On the traffic-calmed north side, the bend screens off a dedicated logistics plaza, ensuring that deliveries and other sensitive traffic flows remain outside the public campus area.

photo_credit Marcel van der Burg
Marcel van der Burg
photo_credit Marcel van der Burg
Marcel van der Burg

From climate chamber to lecture hall
Approximately two-thirds of the building consists of laboratories, each with its own technical requirements: climate and culture chambers, refrigeration and freezer rooms, darkrooms, and biological and chemical laboratories. More than 6,000 m² has been designed in accordance with ML-II requirements, allowing the university to scale the number of contained laboratories up or down as needed without major modifications. In addition, the program includes teaching labs, an auditorium, offices, meeting rooms, an exhibition space, and a lunch area. The building provides space for research facilities that allow interdisciplinary collaboration to flourish in bio-related research at various levels; from molecules to cells to organisms and ecosystems.

photo_credit Marcel van der Burg
Marcel van der Burg
photo_credit Marcel van der Burg
Marcel van der Burg

One heart for knowledge sharing: the living rooms
Innovation arises where organization and space reinforce each other. That is why Leuven Bioscience was designed with a single vision in mind. In the inner corner of the bend runs a vertical series of double- and triple-height spaces: the living rooms. These are the only places where the building’s fixed grid is interrupted. Elevators and restrooms open onto these spaces, and coffee corners, meeting rooms, and flexible workspaces are all brought together here. Researchers from different groups cross paths here every day and can pause for a conversation or to exchange ideas outside their own laboratories.
Each living room has its own atmosphere: more pronounced in the common areas, more subtle in the floor finishes of hallways and laboratories. A cohesive furniture palette connects the zones, while the colors give each part of the building its own identity and aid in orientation. On the facade, the living rooms break up the regular rhythm, making the social hub visible even from the campus. The common areas are concentrated on the upper floors, where the lunch area and the auditorium are located. Since there are no technical installations on the roof, the top floor could also be fitted with a terrace offering a view of the campus.

photo_credit Marcel van der Burg
Marcel van der Burg
photo_credit Marcel van der Burg
Marcel van der Burg

Built for an unknown future
Instead of tailoring each floor to its initial users, the building features a single, virtually universal floor plan across all levels: a three-aisle structure that accommodates any desired combination of laboratories and support offices. Floors without sagging beams, uniform floor-to-ceiling heights and load-bearing capacity, and shafts with reserve capacity ensure that laboratories and offices can switch functions over time. Virtually the entire program can thus be accommodated in virtually any location. This also gave the client the flexibility during the design phase to postpone decisions on the final layout for as long as possible.
The building systems follow the same principle. Ventilation, perhaps the most important system in a laboratory, operates according to a ring concept: supply and exhaust ducts of uniform dimensions form closed rings across each floor and are sized for maximum capacity. It does not matter exactly where the air is extracted. This allows a laboratory to be reconfigured without disrupting the surrounding spaces. The same applies to cooling, water, and gases: strategic sizing and intelligent distribution. The central air-handling unit is located on an intermediate floor halfway through the building’s volume. This shortens the duct runs, keeps the vertical shafts compact, and frees up space for future expansion.
The prefabricated strucure was tailored to the building systems through an iterative design process, ensuring that structural and mechanical elements do not interfere with one another at any point. The structural elements remain exposed, and the number of finishing materials and details has been deliberately limited, which kept construction costs manageable. In this way, Leuven Bioscience Centre functions as an incubator: small and large research groups can carry out their work undisturbed in different locations, in varying configurations, and with changing needs.

Caption

Sustainable through adaptability
The building uses geothermal energy for heating and cooling. Heat recovery and solar panels contribute to the energy supply; rainwater is collected and reused; and LED lighting and energy-efficient elevators minimize energy consumption. Equally important for sustainability is the building’s lifespan: a building that can be adapted without major structural work does not need to be replaced when research priorities change.
The first research groups moved in in June 2026.

Caption

Team:
Client: KU Leuven
Users: KU Leuven (Science & Technology Group, Departments of Biology, M2S, Architecture, Materials Science, Mechanical Engineering, Biosystems, and Chemistry) and the Flemish Institute for Biotechnology (VIB)
Design Team
•    Architecture: Proof of the sum in collaboration with SVR-ARCHITECTS
•    MEP Engineering: Exilab, part of Sweco
•    Structural Engineering: De Klerck Engineering
Construction
•    Water- and wind-tight shell: CIT BLATON
•    MEP: Imtech
•    Laboratory fit-out: Potteau Labo